City of Stuart
WTP - PER-FLUORINATED CHEMICAL TREATMENT SYSTEM
Installation of an 8 MGD ION Exchange System treating PFCs for drinking water; including resin vessels including resin, 100-HP single stage horizontal split case pumps, ductile iron piping and accessories, concrete slab-on-grade, variable frequency drive local control panels, electrical and I&C improvements. At the time of construction, this was the largest resin PFC drinking water system of its kind.
City of Bartow
DOUG ALLEN WRF - CONTROL SYSTEMS UPGRADES
The Project consisted of sequencing batch reactors (SBR) control system upgrades, including constructing a new PLC-based control system for the existing SBR, new field instrumentation for the control system, connecting existing equipment, as well as replacement of existing 200-HP blower motors, and start-up services for the new system.
Brevard County
MIMS WTP - HIGH SERVICE PUMP VFD & PLC REPLACEMENT
The project consisted of replacement of programmable logic controllers control panels, high service pump variable frequency drives, a high service pump motor, along with related electrical and control conduits, wiring, control system programming, SCADA system programming and equipment/ systems startups.
Dixie Park Facility
Demolition & In-Line Booster Pump Station Replacement
The project consisted of demolition of an abandon WWTP and In-Line Booster Pump Station. Construction included modifications to a surge tank, electrical I&C, and construction of an in-line booster pump station.
Naples WTP
Accelator #3 Rehabilitation and Improvements
Complete replacement of an accelator mechanism. Removal of the existing mechanism, lime-sludge, installation of proposed accelator; including rafters, hood plates, gear box, sludge flushing system, and catwalk and coatings.
Lake Wales
Reuse Pump Station - Modifications
Rehabilitation of an existing Reuse Booster Pump Station and ground storage tank. This project consisted of removing pumps and piping, install of 100HP Reuse Pumps, flow meter vault, install of a metal canopy, rehab of a glass-lined ground storage tank, and I&C upgrades.
Deerfield Beach
West WTP Solids Contact Clarifier Rehabilitation
Rehabilitation of an existing 62FT lime softening accelator. Rehab was required to be performed in a short timeframe of 6 weeks which included removal of lime sludge, removal and replacement of a clarifier mechanism metal parts, and final coatings. The project also included refurbishment of 2 Aeration towers including: prep, painting, and media replacement.
Indian River
Hobart RO WTP - Chemical Tanks Replacement
Replacement of a 16,000-gal bulk sulfuric acid tank with a new 12,000-gal horizontal steel storage tank. Replacement of a 5,200-gal bulk caustic tank with a new 5,200-gal horizontal steel storage tank. Replacement of the tanks required new PVCF and secondary containment piping, minor electrical and I&C modifications, and containment coatings
South Martin
Regional Utility
WWTP - Filter & Chlorine Contact Basin Improvements
Installation of (1) 1.6 MGD Disk Filter and rehabilitation of (2) 1.6 MGD existing Disk Filters totaling 4.8 MGD. Installation of a reinforced concrete Chlorine Contact containing (2) chambers. Removal of (2) Traveling Bridge Filters, yard piping, electrical and I&C.
St. Lucie West
WWTP - Filter #2 Replacement
Demolition of an existing traveling bridge filter and installation of (2 EA) 2.0 MGD cloth media disk filters, installation of disk filter equipment, structural modifications, slide gates, piping, electrical system modifications and I&C.